Texas Continued Permitting Data Centers After Abbott’s Pause, Report Finds 

FracTracker and Public Citizen identified 35 permitting actions taken by regulators in Texas in the weeks after Gov. Greg Abbott ordered a moratorium.

Share This Article

The Stargate Oracle AI data center campus is seen on Aug. 26 in Abilene, Texas. Credit: Brandon Bell/Getty Images
The Stargate Oracle AI data center campus is seen on Aug. 26 in Abilene, Texas. Credit: Brandon Bell/Getty Images

Share This Article

Regulators in Texas did not stop processing permits for data center projects when Gov. Greg Abbott ordered a pause last month, according to an analysis of public records released Monday by the oil and gas watchdog group FracTracker. 

Amid an upswell of public opposition to the booming buildout of digital infrastructure in Texas, Abbott directed the Texas Commission on Environmental Quality in a Sept. 21 letter “to halt all permits sought by data centers.”   

But FracTracker, in collaboration with Public Citizen, identified 35 permitting actions taken by the TCEQ for data center projects in subsequent weeks.

“TCEQ has continued reviewing applications and issuing approvals that allow data center development to proceed,” the groups said in a press release Monday. “These actions do not signal an agency trying to pause.”

Newsletters

We deliver climate news to your inbox like nobody else. Every day or once a week, our original stories and digest of the web’s top headlines deliver the full story, for free.

Abbott’s office and the TCEQ did not immediately respond to a request for comment. 

Abbott has described his moratorium on data center projects as an opportunity for state agencies to evaluate the facilities’ impact on water resources and grid stability. 

“No other state agency shall move forward with regulatory approvals related to data centers until this information is acquired,” Abbott wrote in his Sept. 21 letter to TCEQ executive director Kelly Keel. 

Since that letter, the TCEQ has fast-tracked or assigned engineers to 14 permits, approved stormwater coverage for 11, certified emissions estimates for seven and issued public notice for three, according to permitting documents collected by FracTracker and Public Citizen. 

The permits regard construction of gas power generation facilities for energy-hungry facilities. All of the largest gas power projects currently proposed in Texas are specifically intended to serve data centers, which are primarily planned to run artificial intelligence.

The projects would release tens of thousands of tons of regulated pollutants, according to permitting documents, as well as more than 100 million tons per year of greenhouse gases—an enormous amount roughly equal to the annual emissions of a mid-sized industrialized country.

Gov. Greg Abbott (left) shakes hands with Alphabet and Google CEO Sundar Pichai at the Google data center in Midlothian, Texas, on Nov. 14, 2025. Credit: Ron Jenkins/Getty Images
Gov. Greg Abbott (left) shakes hands with Alphabet and Google CEO Sundar Pichai at the Google data center in Midlothian, Texas, on Nov. 14, 2025. Credit: Ron Jenkins/Getty Images

The day after Abbott’s pause on data center permits, on Sept. 22, FracTracker and Public Citizen found that TCEQ mailed notices of preliminary approval to three major projects: NRG Prairie Energy Center, VoltaGrid’s ABI-1 power plant and Nexus’s self-powered data center in Hubbard. 

The agency opened public comment periods on two of those projects in following days. 

FracTracker and Public Citizen found approvals of stormwater management permits for data center construction issued after Sept. 21, including for Caldwell Valley Technology Park in Caldwell County, Crusoe’s Abilene campus and EdgeConneX’s Cedar Creek campus.

The report identified numerous other projects that continue to advance through permitting. For example, records show the TCEQ received a permit application for generators at Edged Energy in Dallas on Oct. 6, and an engineer completed an initial review on Oct. 9.  

“Our research uncovered glaring inconsistencies between regulatory actions and Governor Abbott’s directives,” said Sam Law, manager of communications at FracTracker Alliance and author of the report. “We need an actual pause to study the threats posed to the land, water and livelihoods of Texans.”

About This Story

Perhaps you noticed: This story, like all the news we publish, is free to read. That’s because Inside Climate News is a 501c3 nonprofit organization. We do not charge a subscription fee, lock our news behind a paywall, or clutter our website with ads. We make our news on climate and the environment freely available to you and anyone who wants it.

That’s not all. We also share our news for free with scores of other media organizations around the country. Many of them can’t afford to do environmental journalism of their own. We’ve built bureaus from coast to coast to report local stories, collaborate with local newsrooms and co-publish articles so that this vital work is shared as widely as possible.

Two of us launched ICN in 2007. Six years later we earned a Pulitzer Prize for National Reporting, and now we run the oldest and largest dedicated climate newsroom in the nation. We tell the story in all its complexity. We hold polluters accountable. We expose environmental injustice. We debunk misinformation. We scrutinize solutions and inspire action.

Donations from readers like you fund every aspect of what we do. If you don’t already, will you support our ongoing work, our reporting on the biggest crisis facing our planet, and help us reach even more readers in more places?

Please take a moment to make a tax-deductible donation. Every one of them makes a difference.

Thank you,

Share This Article